Permit-to-work flow for hot works and confined space
Issue, monitor, and close a permit-to-work for hot works or confined space entry from the app.
Practical steps
- 1
Open the permits area. Tap Issue Permit and pick the type: Hot Works, Confined Space, Working at Height, Electrical.
- 2
Fill the named issuer and named recipient. Both are individual people, not job titles.
- 3
Set the valid-from and valid-until times. Permits should never exceed one working day without a re-issue.
- 4
Add the required photos: PPE in place, fire watch present, isolation tag fitted, gas test result.
- 5
Tap Issue. The recipient signs digitally. The permit is live until the valid-until time.
- 6
At the end of the work, close the permit. Add a closing photo and any incident notes.
Key takeaways
- Permits are for named individuals only. Never permit a company or a crew.
- Single-shift validity protects everyone. Anyone wanting longer needs to justify it in writing.
- Close the permit before the valid-until time, with a photo. Lapsed open permits are an HSE finding.